When is a development application made?

Mark Evans • February 15, 2024

In NSW a development application is “made” when the development application is lodged through the NSW planning portal, all of the required documents are provided, the application fee is paid and, finally, notification of lodgement is received by both the applicant and the consent authority.

Only when all of these criteria are met can a development application be said to have been made. This specificity is important because new environmental planning instruments ( EPIs) often contain a savings provision which excludes DAs “made” but not “determined” at the time of introduction of the new EPI. 


This article reviews recent cases dealing with the question of when a DA is “made”.


Commitment Pty Ltd v Georges River Council (No 2) [2022] NSWLEC 94 (Commitment)


In this case the applicability of the Hurstville Local Environmental Plan 2021  HLEP 2012) or the Georges River Local Environmental Plan 2021 (GRLEP 2021) depended on when the development application was made. Clause 1.8A of GRLEP 2021 provides that the GRLEP 2021 does not apply to a development application “made, but not yet determined”, on or before the commencement date of the GRLEP 2021. 


The question in Commitment was whether the Applicant’s development application was “made” on or before the GRLEP 2021 commenced.


Held


Pain J determined at [59] that an Applicant submits a development application via the NSW planning portal, lodges it when the fee is paid and notified as required by cl 50(8) and “makes” the DA when there has been substantial compliance with the regulations. 


Facts 


On 30 September 2021, the development application ( DA ) was submitted to the NSW planning portal.


On 8 October 2021, two things happened: the development application fee was paid and the GRLEP 2021 was published on the NSW legislation website, repealing and replacing the HLEP 2012. 


Section 24 of the Interpretation Act 1987 (NSW) provides that “If an Act or statutory rule provides that it shall commence, or be deemed to have commenced, on a particular day, it shall commence, or be deemed to have commenced, at the beginning of that day.” 


Both parties agreed that the GRLEP 2021 came into force very early on 8 October 2021.


Clause 1.8A of GRLEP 2021 contains the relevant savings provision:


1.8A Savings provisions relating to development applications

If a development application has been made before the commencement of this Plan in relation to land to which this Plan applies and the application has not been finally determined before that commencement, the application must be determined as if this Plan had not commenced.


[our emphasis]


When the DA was submitted to the NSW planning portal (30 September 2021) the Environmental Planning and Assessment Regulation 2000 (EPA Regulation 2000) applied. Clause 50 of the EPA Regulation 2000 set out the requirements for a development application to be “made”:


50 How must a development application be made? 


(1)  A development application must – 

(a)  be in the form that is approved by the planning secretary and made available on the NSW planning portal,


(b) contain all of the information that is specified in the approved form or required by the Act and this Regulation, and


(c)  be accompanied by the information and documents that are specified in Part 1 of Schedule 1 or required by the Act and this Regulation,


(d)  be lodged on the NSW planning portal.


(8)  The applicant must be notified, by means of the NSW planning portal, that the development application has been lodged.

(9)  A development application is taken not to have been lodged until the fees notified to the applicant by means of the NSW planning portal have been paid.


Note: The Environmental Planning and Assessment Regulation 2021 (EPA Regulation 2021) repealed and replaced the EPA Regulation 2000. Clause 50 of the EPA Regulation 2000 became clause 24 in the EPA Regulation 2021 and contains similar language and similar provisions.


The Applicant argued that a development application is “made” when it is uploaded to the NSW planning portal and contains the documents and information required by the EPA Regulation 2000. 


Moreover, under s 4.12(1) and (2) of the EPA Act an application may be made by ‘a person’, not a consent authority. Accordingly, persons other than an Applicant cannot determine if an application is “made” given the entitlement of a person to apply granted by s 4.12 of the EPA Act. An Applicant’s entitlement to make a development application under s 4.12 of the EPA Act is frustrated by a construction whereby ‘lodgement’ must be satisfied in order for an application to be made when that is clearly a separate process and outside the control of the Applicant. 


The Council argued that the lodgement of a DA on the NSW planning portal is one aspect of the making of a DA such that a DA could not be made simply when “put” onto the NSW planning portal by the applicant. To accept this construction gives the EPA Act and EPA Regulation 2000 no work to do. Lodgement on the planning portal is a necessary pre-requisite to a DA being “made” and lodgement is expressly contingent on payment of the relevant fee. 


Decision


The Court held (at [47]) that a DA is made for the purposes of the savings provision in cl 1.8A of the GRLEP 2021 when there is substantial compliance with each of the requirements of the EPA Act and EPA Regulation 2000 applicable to the making of development applications. This includes all of the requirements of cl 50 (above) and payment of the fee. 


Pain J found at [50] that, “Arguably only once substantial compliance with cl 50(1) is achieved has a DA been made sufficient to enable its determination. One requirement is that “lodgement” of a DA is required by cl 50(1)(d) and must be read with subcl (9) (the requirement to pay a fee).”


Pain J held (at [56]), that whether a matter is within a person’s control, or not, is not relevant to statutory construction. In this case, it was irrelevant whether the Applicant was in control of when the DA was made for the purposes of construing the legislation.


The Court agreed with the Council’s argument that an applicant submits the DA via the NSW planning portal and obtains a unique PAN number, lodges it when the fee is paid and notified and “makes” the DA when there is substantial compliance with all of the requirements of cl 50 of the EPA Regulation 2000.


Key Takeaways


  • An Applicant submits a DA via the NSW planning portal and obtains a unique PAN number, lodges it when the fee is paid and “makes” the DA when there is substantial compliance with cl 50 of the EPA Regulation 2000.


  • Whether matters outside the control of the Applicant delay or impact the date a DA is “made” is not relevant to the exercise of statutory construction required to determine when a DA has been made.


Hinkler Ave 1 Pty Limited v Sutherland Shire Council [2022] NSWLEC 150


Similar to Commitment, at the core of this case was a dispute about when a development application was made. 


The applicability of the State Environmental Planning Policy (Housing) 2021 (2021 SEPP), depended on when the development application was made. On 26 November 2021, the 2021 SEPP repealed and replaced the State Environmental Planning Policy (Affordable Rental Housing) 2009 (2009 SEPP). The 2021 SEPP has different standards and requirements to those of the 2009 SEPP, which restricted the Applicant’s proposed development. 


The 2021 SEPP contained a savings provision which, if satisfied for the Applicant’s development application, would mandate that the application was determined pursuant to the old 2009 SEPP, not the new 2021 SEPP.


The question in this case was whether the Applicant’s development application was “made” on or before the 2021 SEPP commenced.


Held


Moore J determined that the Applicant’s development application was not made on or before the 2021 SEPP commenced. Moore J found that, as at 26 November 2021, the development application was not accompanied by either the A4 plan of the building required by cl 50(1)(c) and cl 2(1)(d) of Sch 1 of the EPA Regulation 2000 (at [59], [60], [67], [68], [71]) or payment of a fee duly determined and notified to the Applicant (at [61]-[64], [73]).


Facts 


The Applicant submitted a development application through the NSW planning portal on 22 October 2021. Exchanges between the Applicant and the Council seeking further information about the development application took place after 22 October 2021.


The EPA Regulation 2000 requires a number of documents, plans and information to be uploaded to the NSW planning portal to form a complete application. Schedule 1, 2(d) of the EPA Regulation 2000 requires:


(d) in the case of development that involves the erection of a building, an A4 plan of the building that indicates its height and external configuration, as erected, in relation to its site (as referred to in clause 56 of this Regulation),


The development application was not accompanied by “an A4 plan of the building that indicates its height and external configurations, as erected, in relation to its site”. Other plans of the buildings to be erected on the site (the proposed development comprised four buildings), from which the heights and external configurations of the buildings could be derived, did accompany the development application. But there was no single A4 plan of the buildings that indicated their heights and external configurations.


The consent authority, Sutherland Shire Council (Council), issued requests for additional information, first on 23 November 2021 and again on 29 November 2021. The Applicant issued a response to those requests on the NSW planning portal on 26 November 2021 and 1 December 2021 respectively. Although the Applicant did supply further plans, it never supplied a single A4 plan of the buildings that indicated their heights and external configurations.


On 2 December 2021 the Council issued an invoice for the development application fee through the NSW planning portal. The Applicant paid the invoice on 9 December 2021. 


The parties sought determination of a legal question: for the purpose of the savings provision in the 2021 SEPP, was the development application to be regarded as having been made on or before 26 November 2021 when the new 2021 SEPP commenced?


The EPA Regulation 2000 applied at the time. Clause 256(1) of the EPA Regulation 2000 required that the Council raise an invoice within 14 days of receiving an application. 


Note: Following the introduction of the new EPA Regulation 2021 this requirement remains and is found in cl 256 of the EPA Regulation 2021.


The Applicant argued that the failure of the Council to discharge its mandatory obligation under cl 256(1) of the EPA Regulation 2000 should not be permitted to stand in the way of the conclusion that the Applicant’s development application had been made, but not determined, on or before 26 November 2021. Further, the Applicant had substantially and sufficiently complied with the requirements of the EPA Regulation 2000 by 26 November 2021 so that the Applicant’s development application should be held to have been made by that date.


The Council argued that the plans which satisfied the EPA Regulation 2000 were not uploaded by the Applicant until 1 December 2021. This meant that the obligation to determine and notify the development application fee as required by cl 256(1) of the EPA Regulation 2000 was not triggered until those plans, which were compliant with Sch 1, cl 2(d) of the EPA Regulation 2000, were uploaded to the NSW planning portal on 1 December 2021.


Decision


Moore J applied the analysis of Pain J in Commitment (above) concerning the relevant steps in the process necessary to regard a development application as being “made”. For the reasons explained in Commitment a development application can only be regarded as having been made after the fee payable for such a development application has been paid.


In this instance, the Applicant had not uploaded the A4 plan required until 1 December 2021, nor paid the applicable fee until 9 December 2021, both of which were required prior to a development application being “made”.


Moore J found that there was no evidence the Applicant had rejected the validity of the Council’s requests for further information between 22 October 2021 (DA submitted) and 2 December 2021 (invoice raised) and the Applicant’s planner should have done so if it felt the Council had no justification to raise the questions it did. 


Further, Moore J held that in circumstances in which the Applicant asserts that the Council breached its obligations in the EPA Regulation 2000 it was open to the Applicant during this time to bring urgent proceedings in of the Land and Environment Court to remedy the alleged breach by the Council. The breach could have been remedied by the Applicant exercising its right pursuant to s 9.45 of the EPA Act and approach the Court to seek an order to require the Council to determine and advise the Applicant of the development application fee payable. 


Key Takeaways


  • A DA is “made” for the purposes of savings provisions when it is submitted to the NSW planning portal and the fee is paid.


  • Following submission of the DA into the NSW planning portal, a consent authority has 14 days to raise an invoice for payment of the applicable development application fee.


  • If a Council refuses to raise the invoice for payment and requests additional information to accompany the application in accordance with the requirements of the regulations, Applicants should consider carefully whether their application is compliant and, if it is, state that fact very clearly in written communication to the Council.


  • Where a Council breaches its obligation to raise the invoice for payment in time, it is open to Applicants to bring urgent proceedings in Class 4 of the Land and Environment Court to remedy the breach.


Hinkler Ave 1 Pty Limited v Sutherland Shire Council [2023] NSWCA 264


The Applicant appealed the decision of Moore J (at first instance) to the NSW Court of Appeal. 


Held


Basten AJA (with whom Gleeson JA agreed) and Preston CJ of the Land and Environment Court (dismissing the appeal) held that on a proper construction of the statutory provisions governing the making of a development application, the Applicant’s development application was not “made” on or before the commencement date of the 2021 SEPP. Accordingly, Moore J was correct in finding that the 2021 SEPP and not the 2009 SEPP applied to the Applicant’s development application. Preston CJ set out the statutory scheme for making development applications to resolve the competing interpretations advanced by the parties.


The analysis provided by Preston CJ is especially helpful for town planners in understanding the requirements of making development applications.


Statutory scheme for making development applications


Section 4.12(1) of the EPA Act states simply that a “person may, subject to the regulations, apply to a consent authority for consent to carry out development”. The relevant regulation in force at the time the Applicant made the development application was the EPA Regulation 2000. 


Clause 50 of the EPA Regulation 2000 prescribed how a development application must be made and clause 50(1) prescribed the form and manner of making a development application for consent to carry out development (other than state significant development). 


Clause 50 provided:


(1) A development application, other than an application for State significant development, must—


(a)  be in the form that is approved by the Planning Secretary and made available on the NSW planning portal, and


(b)  contain all of the information that is specified in the approved form or required by the Act and this Regulation, and


(c)  be accompanied by the information and documents that are specified in Part 1 of Schedule 1 or required by the Act and this Regulation, and


(d)  be lodged on the NSW planning portal.


Paragraphs (a) to (c) prescribe the form the development application must take, paragraph (d) prescribes the manner in which the application must be lodged, via the NSW planning portal.


His Honour Preston CJ held that the first type of information that was required in this case to be provided included an A4 plan to accompany the development application. Although the Applicant’s development application included a series of plans of the buildings, the development application was not accompanied by an “A4 plan” of the buildings that indicated their heights and external configurations, as erected in relation to the site. The Applicant provided an A3 site plan and five A3 sheets of elevations, which were extracts from the full set of plans.


Accordingly, Preston CJ found at [94] that “the requirement that such an A4 plan accompany the development application remained unmet as at the commencement date of the 2021 SEPP of 26 November 2021.”


His Honour held that the second type of information (or document) that was required to accompany the development application was the payment (or record of payment) of the fee to accompany the development application. This is because clause 256 of the EPA Regulation 2000 requires that the consent authority make a determination of the fee to “accompany a development application” and to notify the Applicant of the determination.


Preston CJ held at [98] that clause 256 of the EPA Regulation 2000 imposes a requirement on the Applicant that payment of a fee, which has been determined by the Council and notified to the Applicant, “accompany a development application”. Accordingly, this Honour held:


“The payment of a duly determined and notified fee thus falls within the category of “information and documents that are specified in Part 1 of Schedule 1 or required by the Act and this Regulation”, which cl 50(1)(c) of the EPA Regulation 2000 requires a development application to be accompanied by.”


His Honour held at [99] that the consequence of the Applicant’s development application not “meeting these two form requirements that the development application be accompanied by the A4 plan of the building and the payment of the fee was that the development application was incomplete as at 26 November 2021.”


Incomplete and ineffective application


His Honour went on to discuss the nature of an incomplete application being ineffective, that is, not being capable of engaging the power of the consent authority to grant consent to the application.


The wording of the savings provision in the 2021 SEPP (a development application “made” but not yet “determined”) presupposes that there is a complete and effective development application that can be “determined” by the grant of consent. His Honour held at [118]:


“The consent authority would have no power to determine by the grant of consent a development application that is incomplete and ineffective. Thus, both the word “made” and the word “determined” demand that the development application be complete and effective in order to be an application in terms of the EPA Act.”


What about the deeming provision in cl 50(9) of the EPA Regulation 2000?


Recall that cl 50(9) of the EPA Regulation 2000 provides:


(9) A development application is taken not to have been lodged until the fees notified to the applicant by means of the NSW planning portal have been paid.


His Honour found at [125] that “The deeming provision in cl 50(9) operates to deem a development application, although in fact lodged on the NSW planning portal under cl 50(1)(d), not to have been lodged until the fees notified to the applicant by means of the NSW planning portal have been paid.”


The lodging of the development application on the planning portal is the way in which the application must be made. Cl 50(9) has 2 effects:


  1. it deems a development application that has been lodged on the portal not to have been lodged; and
  2. it also causes a development application not to have been “made” until the fee notified to the Applicant has been paid.


Accordingly, his Honour stated at [129]: “A development application that is not lodged is not made. Thus, cl 50(9) operates not only to deem a development application not to have been “lodged” until the fee notified to the applicant has been paid, but also to cause the development application not to be “made” as the manner requirement for making a development application would not be satisfied.”


In summary, Preston CJ found that the Applicant’s development application was incomplete and ineffective because it was not accompanied by the A4 plans and payment of the fee. Neither occurred before the commencement of the 2021 SEPP on 26 November 2021. As a consequence, the development application was not “made” for the purpose of the savings provision and the 2021 SEPP applied, not the former 2009 SEPP. 


DA not made until Applicant notified of payment


Basten AJA (with whom Gleeson JA agreed) held at [28] that the development application is “made” when the consent authority provides a notification that the application is lodged after the fee has been paid. It is the date of notification of payment of the fee, not the date of payment of the fee itself which is the relevant date. 


Basten AJA found that cl 50 of the EPA Regulation 2000 sets out a number of steps that must occur in the making of a development application, namely, the lodging on the NSW planning portal, the notification to the Applicant of the fee payable, payment of the fee and, finally, notification through the NSW planning portal that the development application has been lodged (cl 50(8)). 


Recall that cl 50(8) of the EPA Regulation 2000 provides:


50   How must a development application be made?

(8) The applicant must be notified, by means of the NSW planning portal, that the development application has been lodged.


(9) A development application is taken not to have been lodged until the fees notified to the applicant by means of the NSW planning portal have been paid.


His Honour held at [27] – [28]:


“[27] … On one view, that [the finding of a precise date the development application is made] is the purpose and effect of cl 50(8), which requires that the applicant be notified that the development application has been lodged.


[28] Mechanically, the notice is generated by the NSW planning portal itself. However, that must be a result of steps taken by a party to the process. It is clearly not the applicant that directly causes the notice to be given, because it is the recipient of the notice. The purpose of the notice is to let the applicant know that lodgement is complete. The only other party which can cause the giving of the notice is the consent authority. On that view, the application is lodged when the consent authority provides a notification to that effect on the NSW planning portal….”


Key Takeaways


  • The Court of Appeal upheld Moore J’s findings in the first instance.


  • A development application is incomplete if it is not accompanied by payment of the relevant fee.


  • A development application is taken to have been made not when the application fee is paid, but when both the Council and the Applicant are notified through the NSW planning portal that the application is lodged (pursuant to cl 50(8) of the EPA Regulation 2000).


Summary


  • In NSW a development application is “made” for the purposes of most savings provisions, when the application fee is paid, compliance with the requirements of the regulation is achieved and when notification of lodgement via the NSW planning portal is received.


  • Where an applicant considers requests for additional information are unwarranted or have been satisfied it should state this early in writing and provide reasons.


  • Non-compliance with requirements for development applications in the regulations will result in an ineffective development application that does not engage the power of the consent authority to grant consent to the application. 


  • In circumstances where the Council delays or refuses to raise an invoice for payment of the application fee an Applicant may bring proceedings in Class 4 of the Land and Environment Court to remedy the breach. 


Require further assistance?


We have assisted many applicants and town planners negotiating issues with acceptance of development applications into the NSW planning portal by Council and the raising of invoices for payment. As demonstrated by the cases above, the date a development application is made can have serious implications.


If you require advice regarding when your development application may have been “made” or are considering approaching the Land and Environment Court for relief against a failure to raise an invoice or accept a development application, we can assist you in this process.




Please do not hesitate to call us on (02) 9145 0900 or make an enquiry below.

A man in a suit is sitting on the steps of a building.

Servicing all of NSW, Whiteacre provides expert property law and planning and environment law advice and assistance.

Planning Law Advice

Land and Environment Court Appeals

Voluntary Planning Agreements and Contributions

Development Control Orders and Enforcement

Property Development Advice and Due Diligence

Title Structuring

Easements and Covenants

Strata and Community Title legislation

Book an initial consultation through our website with our planning law solicitor. Whether it's about planning and environment law or property law, you can approach us and discuss your matter to make sure we are a good fit for your requirements.

BOOK ONLINE
By Mark Evans May 4, 2025
This article provides a general overview of the NSW Biodiversity Offsets Scheme, followed by a discussion of the tax implications of establishing a biodiversity stewardship site for Councils. What is the NSW Biodiversity Offsets Scheme? The NSW Biodiversity Offsets Scheme (the Scheme ) is a market-based scheme that is administered by the NSW Department of Climate Change, Energy, the Environment and Water ( Department ) and aims to help address the loss of biodiversity and threatened species in NSW. It seeks to do so by creating incentives for landowners to improve or maintain biodiversity values as a means of offsetting impacts on other areas. The Scheme is established by the Biodiversity Conservation Act 2016 ( BC Act ) . How the Scheme works Councils can establish a ‘biodiversity stewardship site’ ( Stewardship Site ) on eligible land within NSW by means of entering into a Biodiversity Stewardship Agreement ( Stewardship Agreement ) with the Department: s 6.17 BC Act. In doing so, Councils commit themselves to enhancing and protecting biodiversity values on the Stewardship Site. On execution of a Stewardship Agreement, the Council is entitled to receive an amount of biodiversity credits which are created by the Department. The amount of biodiversity credits are calculated by the Council’s accredited ecologist (and verified by the Department) in accordance with the methodology prescribed in the Biodiversity Assessment Method ( BAM ): s 6.7 BC Act. Biodiversity credits are created in respect of existing biodiversity values on the land and management actions to be carried out in accordance with the Stewardship Agreement. A biodiversity credit remains in force unless it is cancelled or retired: s 6.18 BC Act. The market value of the biodiversity credits is calculated by the Department at the time of creation. Sale and transfer of biodiversity credits Biodiversity credits may be sold by the Council to a buyer (or in parcels to a number of buyers) seeking to offset the impact of actions detrimental to biodiversity or to permanently secure conservation outcomes. The sale price of the biodiversity credits is determined by agreement between the Council and the buyer. Alternatively, biodiversity credits may be used by Council to offset negative biodiversity impacts arising from an activity carried out under Part 5 of the Environmental Planning and Assessment Act 1979 : s 7.15 BC Act. The Council may transfer biodiversity credits to a buyer or third party: s 6.19 BC Act. The transfer is made through an application to the Department by the parties to the transfer. The transfer is not effective until the transfer is authorised by the Department and registered in the register of biodiversity credits: s 6.20 BC Act. On the registration of the first transfer of the biodiversity credits, the Total Fund Deposit ( TFD ) specified in the Stewardship Agreement (or a proportion, if not all the credits are transferred) is required to be paid by the buyer of the biodiversity credits into the Biodiversity Stewardship Payments Fund (the Fund ): s 6.21 BC Act. The TFD is a fixed amount of money used to cover the long-term management costs of a Stewardship Site. It is a calculated value representing the present value of future payments needed to fund the agreed management actions. Contracts for the sale of biodiversity credits between the Council and purchasers will state that the credit owner is entitled to the full amount of the agreed sale price of the biodiversity credits, including the TFD, and that the credit owner will have the obligation to pay the TFD. Once the credits have been ‘used’ to offset negative biodiversity impacts and to permanently secure the conservation of biodiversity, they are ‘retired’ such that they can no longer be used for any other purpose: s 6.27 BC Act. Annual payments are made out of the Fund to the Council in respect of management actions carried out in accordance with the Stewardship Agreement: s 6.34 BC Act. Management actions typically include obligations to fence areas of land, control exotic pest species, carry out bushfire management and weed management. In summary, annual payments made out of the Fund can help Councils meet the expenses they currently incur managing large tracts of land while achieving significant biodiversity conservation outcomes. Disclaimer This is a general overview of the Scheme and tax implications. The information in this article is general in nature and is intended as a guide only. It is not designed to be, nor should it be regarded, as legal or accounting advice. The business and financial structure for each landholder or entity managing a biodiversity stewardship site or conservation area is likely to be unique. Therefore, the way taxation law applies will depend on individual circumstances and you should consult a professional tax adviser before engaging with the Scheme or entering into a Stewardship Agreement. Capital Gains The ATO deems that a capital gains event (type D4) occurs on entry into a Stewardship Agreement: s 104-47(1) ITAA. The landowner makes a capital gain if the “capital proceeds” are more than that part of the “cost base” of the land that is apportioned to the covenant. Most state and federal government departments, including local councils are tax exempt: s 50.25 ITAA. GST on entry into Stewardship Agreement When the Department and the Council enter into a Stewardship Agreement, the Council makes a taxable supply by entering into the agreement in return for the biodiversity credits issued by the Department and the Department makes a taxable supply of biodiversity credits in return for the Council entering into the agreement. These are non-monetary transactions. The Department and the Council (if both are registered for GST): are required to pay GST in respect of their supply, calculated on the estimated value of the credits; and can claim an input tax credit (ITC) in respect of the tax invoice received from the other party. If a Council is registered for GST, the Department will issue a Department GST invoice and Recipient Created Tax Invoice (RCTI) on behalf of the Council when the Department sends the registered BSA to the Council. The Department will use the estimated market value of the biodiversity credits for the purposes of these invoices. As the GST payable and the input tax credit that can be claimed are the same amount, the net GST position for both the Council and Department is zero. This means that these invoices do not need to be paid. However, both the Department and the Council are required to account for the GST payment and the input tax credit in their business activity statements (BAS). Capital gains from sale or transfer of credits A CGT event (type A1) occurs upon the sale of biodiversity credits. The Council may make a capital gain or loss depending on the capital proceeds and cost base of the credits: s 104-10(4) of the ITAA. A biodiversity credit constitutes a CGT asset: s 108-5 of the ITAA. CGT event (type A1) happens when the Council disposes of biodiversity credits: s 104-10 of the ITAA. Most state and federal government departments, including local councils are tax exempt: s 50.25 ITAA. GST on sale of biodiversity credits For the purposes of GST, the sale of credits is a taxable supply of goods. This means that the biodiversity credit price should include GST that the Council then needs to pay to the ATO. Receipt of annual payments from the Biobanking Trust Fund Annual payments from the Fund made by the Department to the Council are a contractual payment for the performance of services and should be ordinary income and assessable for income tax purposes. Most state and federal government departments, including local councils are tax exempt: s 50.25 ITAA . GST on annual payments The supply of stewardship services by the Council to the Department in return for payment of the annual payment should be a taxable supply. The Department will issue a recipient created tax invoice (RCTI) and include an amount for GST when making the annual stewardship payments for management actions the Council delivers. Conclusion Councils can establish biodiversity stewardship sites on eligible land within NSW by means of entering into a Biodiversity Stewardship Agreements with the Secretary of the Department. On execution of a Stewardship Agreement, the Council is entitled to receive an amount of biodiversity credits. Biodiversity credits may be sold by the Council to a buyer seeking to offset the impact of actions detrimental to biodiversity or to permanently secure conservation outcomes. Biodiversity credits may be used by Council to offset negative biodiversity impacts arising from an activity carried out by Council. Some of the proceeds of the sale of biodiversity credits must be paid into the Fund to cover ongoing management actions and costs. Annual payments are made out of the Fund to the Council in respect of management actions carried out in accordance with the Stewardship Agreement. Management actions typically include obligations to fence areas of land, control exotic pest species, carry out bushfire management and weed management. In summary, annual payments made out of the Fund could help Councils meet the expenses they currently incur managing large tracts of land while achieving significant biodiversity preservation outcomes. Disclaimer This is a general overview of the Scheme and tax implications. The information in this article is general in nature and is intended as a guide only. It is not designed to be, nor should it be regarded, as legal or accounting advice. The business and financial structure for each landholder or entity managing a biodiversity stewardship site or conservation area is likely to be unique. Therefore, the way taxation law applies will depend on individual circumstances and you should consult a professional tax adviser before engaging with the Scheme or entering into a Stewardship Agreement.
Navigating Land and Environment Court
By Mark Evans March 20, 2025
Expert Legal Insights on Development Approvals and Appeals with Planning Lawyer Mark Evans
Physical Commencement of Development Consents
By Mark Evans February 27, 2025
Development consents granted after 15 May 2020 face stricter requirements to determine whether they are substantially commenced and thus remain valid. This article reviews recent case law in New South Wales (NSW) and outlines the types of work that can qualify as physical commencement.
shared driveways
By Mark Evans February 13, 2025
Shared driveways A common example of a shared driveway is where a right of carriageway passes through one neighbours’ (burdened) land into the other neighbour’s (benefited) land.
tiny homes
By Mark Evans November 27, 2024
In Part 1, we considered tiny homes and caravans on private land. That article can be accessed here Part 1 . In Part 2, we turn our attention to tiny homes and manufactured homes.
tiny homes
By Mark Evans November 22, 2024
In this article we explore tiny homes, caravans, and manufactured homes.
By Mark Evans and William Jamieson November 14, 2024
The general rule is that a development application ( DA ) is to be determined based on the law applicable at the time of determination of the DA, not at the time of lodgement: Sofi v Wollondilly Shire Council (1975) 31 LGERA 416.
When subdivision may not be considered development carried out on land
By Mark Evans and William Jamieson October 31, 2024
Subdivision, alone, may not constitute development “on land” and thus trigger development restrictions. 
Biodiversity Credits
By Mark Evans October 18, 2024
The Independent Pricing and Regulatory Tribunal (IPART) has released a summary of workshops and stakeholders’ submissions concerning the functioning of the NSW Biodiversity Credits Market.
Development
By Mark Evans and William Jamieson October 10, 2024
It is now well established that a development consent cannot be obtained to authorise works that have already been carried out. The classic example is a building that has been built without development consent.
More Posts