Rejection of Development Applications in NSW: Understanding Your Rights
The number of development applications that are rejected prior to assessment has risen noticeably since mandatory online lodgement via the NSW Planning Portal was introduced.
Local councils are increasingly employing two mechanisms to reduce the number of applications under assessment. The first is outright rejection — returning applications on the stated basis that required documents or information are missing. The second is more passive but equally damaging: not issuing an invoice for assessment fees, leaving the application suspended in a state where it cannot be formally lodged and cannot advance.
Both mechanisms carry real consequences for applicants. A development application (DA) that is rejected or that has not been formally lodged attracts no assessment obligations from the consent authority, no appeal rights in the Land and Environment Court of NSW (LEC), and no protection against planning controls that may change in the interim.
This article sets out the legal rules that govern pre-lodgement rejection, explains why invoice delay can be just as harmful as outright rejection, and identifies the avenues available to applicants who find themselves in this position.
The legal rules governing pre-lodgement rejection
Section 39 of the Environmental Planning and Assessment Regulation 2021 (EP&A Reg) outlines the circumstances in which a consent authority can reject a DA at the pre-lodgement stage. The provision is deliberately narrow. A council may only exercise this power:
- on one of the specific grounds set out in section 39(1)(a) to (f) of the EP&A Reg; and
- within 14 days of receiving the DA via the NSW Planning Portal.
The mirror provisions for modification applications are found at section 114(1)(a) to (d) of the EP&A Reg.
Any rejection that falls outside this framework — whether because it is issued after the 14-day period has elapsed, or because it relies on grounds not found in the EP&A Reg — is legally invalid. It is an exercise of power the council simply does not have, and is open to challenge in Class 4 of the LEC's jurisdiction.
The grounds on which rejection is permitted
Section 39(1) of the EP&A Reg provides:
(1) A consent authority may reject a development application within 14 days after receiving the application if —
(a) the application is illegible or unclear about the development consent sought, or
(b) the application does not contain the information and documents that are required by — (i) the approved form, or (ii) the Act or this Regulation, or
(c) for an application for State significant development — the Planning Secretary considers the application incomplete for reasons given by written notice to the applicant, or
(d) for an application for integrated development — the application does not identify all of the approvals required to be obtained, as referred to in the Act, section 4.46, before the development may be carried out, or
(e) for an application required to be accompanied by a biodiversity development assessment report under the Biodiversity Conservation Act 2016 — the application is not accompanied by a report, or
(f) for an application required to be accompanied by a species impact statement under the Fisheries Management Act 1994, section 221ZW — the application is not accompanied by a statement.
The reference in section 39(1)(b)(i) to the 'approved form' relates to the form approved by the Planning Secretary and published on the NSW Planning Portal, as defined in Schedule 7 of the EP&A Reg. The relevant document at the date of this article is the Department of Planning and Environment's Application Requirements (March 2022).
Essentially, the permissible grounds for rejecting a standard DA are that it is illegible or unclear, that it omits material required by the approved form, or that it omits material expressly required by the EP&A Act or EP&A Reg.
One point warrants emphasis above all others: a council cannot reject a DA at the pre-lodgement stage on matters of merit. Councils occasionally attempt to return applications because their preliminary view is that the application will not be approved, or because the plans appear to involve non-compliances. This is not a lawful basis for rejection. The pre-lodgement gateway exists only to verify that the prescribed documents and information have been provided. Consideration of the merits — under the framework in section 4.15(1) of the EP&A Act — is reserved for the assessment stage, which begins only after lodgement. A merit-based rejection will almost invariably be susceptible to challenge.
The 14-day window and the problem of invoice delay
A council's power to reject a DA or modification at the pre-lodgement stage expires 14 days after the application is received via the NSW Planning Portal. A rejection notified after that point is legally invalid. We have observed councils purporting to reject applications well outside the 14-day window, sometimes by weeks or months, and in our experience applicants rarely challenge this.
A separate but equally serious problem arises where a council does not reject the DA — but also does not issue an invoice for assessment fees. The NSW Court of Appeal and the LEC have now clearly held that a DA is only formally 'lodged' once the invoice has been issued and the fee paid: Hinkler Ave 1 Pty Limited v Sutherland Shire Council [2023] NSWCA 264; Commitment Pty Ltd v Georges River Council(No 2) [2022] NSWLEC 94. Because a DA is only formally 'lodged' once the invoice has been issued and the fee paid, a council that withholds the invoice can hold an application in permanent limbo without ever technically rejecting it.
The same rule applies to modification applications by virtue of section 99(4) of the EP&A Reg.
An application that has not been lodged in this sense cannot proceed to assessment, generates no appeal rights, and remains exposed to any change in applicable planning controls that occurs after submission. The stakes could not be higher, as the facts of Hinkler Ave 1 Pty Ltd v Sutherland Shire Council [2023] NSWCA 264 (Hinkler) demonstrate.
In Hinkler, the applicant uploaded a DA for a mixed-use development incorporating affordable housing to the NSW Planning Portal on 22 October 2021. No invoice was issued by the council until 2 December 2021 — five weeks after submission. During that window, on 26 November 2021, the SEPP (Affordable Rental Housing) 2009 (SEPP ARH) was replaced by the SEPP (Housing) 2021 (SEPP Housing). A savings provision in the SEPP Housing preserved rights for DAs already 'made' before its commencement. Had the invoice been issued and paid before 26 November 2021, the applicant would have been entitled to rely on the former SEPP ARH. Because it was not, the Court of Appeal held the DA was not 'made' in time, and the applicant was required to satisfy the more demanding requirements of the new SEPP Housing.
At paragraph [159], Preston CJ (of LEC) noted that a council's failure to issue an invoice within a reasonable time may constitute a breach of statutory duty, and that an applicant in that position may seek an order of mandamus compelling the council to fulfil its obligation.
Options available to applicants
Applicants faced with an unlawful rejection or an unreasonable invoice delay have genuine legal options.
Internal review under section 8.2 of the EP&A Act allows a council to reconsider its own decision. Supported by clear written submissions identifying why the rejection was not authorised by the EP&A Reg, this process can produce a faster and less costly resolution than litigation — particularly where the council's position appears to rest on a misreading of the application rather than a deliberate strategy.
Judicial review is available in Class 4 of the LEC where a jurisdictional error can be established. Depending on the circumstances, an applicant may seek:
- certiorari to quash the rejection decision;
- mandamus to compel the council to accept the application and issue an invoice; and
- declaratory relief confirming that the rejection was unlawful.
If your DA or modification application has been rejected on questionable grounds, rejected outside the 14-day window, or if an invoice has not been issued within a reasonable period, we recommend seeking legal advice without delay. The consequences of inaction — including exposure to changed planning controls — can be irreversible.
The contents of this article are a general guide and intended for educational purposes only. Determination of issues of the kind discussed in this article is often complex and varies greatly from case to case. Each individual case is different and requires a detailed understanding of matters of fact and degree upon which reasonable minds may differ.
DO NOT RELY ON THIS ARTICLE AS A SUBSTITUTE FOR COMPETENT LEGAL ADVICE.
Browse by categories

Servicing all of NSW, Whiteacre provides expert property law and planning and environment law advice and assistance.
✓ Planning Law Advice
✓ Land and Environment Court Appeals
✓ Voluntary Planning Agreements and Contributions
✓ Development Control Orders and Enforcement
✓ Property Development Advice and Due Diligence
✓ Title Structuring
✓ Easements and Covenants
✓
Strata and Community Title legislation
Book an initial consultation through our website with our planning law solicitor. Whether it's about planning and environment law or property law, you can approach us and discuss your matter to make sure we are a good fit for your requirements.