“Existing” ground level – what it is and how it is determined

Mark Evans • March 7, 2024

Most land in NSW is subject to controls which limit the height of buildings in a neighbourhood. The height control is usually expressed as the height of a building (in metres) above “existing” ground level. But, determining “existing” ground level can be difficult, for example where the site has been heavily excavated, built upon or is irregular in form. This article considers the definition of existing ground level in NSW planning law and cases in the NSW Land and Environment Court.

Usually, the height of building control takes the form of clause 4.3 in most local environmental plans:


“4.3(2) The height of a building on any land is not to exceed the maximum height shown for the land on the Height of Buildings Map.”


The Height of Buildings Map will (usually) prescribe a maximum height, for example 8.5 metres or 12 metres. The “height of a building” is defined in the Standard Instrument as:


building height (or height of building) means—


(a) in relation to the height of a building in metres—the vertical distance from ground level (existing) to the highest point of the building, or


(b) in relation to the RL of a building—the vertical distance from the Australian Height Datum to the highest point of the building,


including plant and lift overruns, but excluding communication devices, antennae, satellite dishes, masts, flagpoles, chimneys, flues and the like”.


(our emphasis)


Accordingly, the highest point of a building (excluding lift overruns etc) must not be higher than the specified height (eg 8.5m) above the existing ground level. 


Existing ground level is defined in the Standard Instrument as: 


ground level (existing) means the existing level of a site at any point.”


Determining the ground level (existing) can be challenging where excavation has occurred on the site, where the site contains irregularities or where an existing building occupies the entire site.


These challenges and how they have been dealt with in the NSW Land and Environment Court (Court) are illustrated in the cases below.


Land that has been excavated or built upon


Bettar v Council of the City of Sydney [2014] NSWLEC 1070 (Bettar)


Facts 


Consent was sought for a four and five storey residential flat building. An existing building occupied the entire site such that there was no longer any “ground” on the site from which “ground level (existing)” could be measured.


Council submitted that the ground level (existing) should be the ground floor of the existing building.


The Applicant submitted that the ground level (existing) ought to be extrapolated from the footpath and surrounding levels on neighbouring sites, rather than the ground floor of the building.


Decision


The Court held that once the existing building was demolished it would be impossible to determine the natural ground level and the former building on the site could no longer be discernible or relevant as a starting point for measuring the height of any new building. It would be conceivable that surrounding properties (each with existing buildings already built upon them) could end up with a variety of different height limits arising under the same development standard.


Further, the Commissioner held that Council’s approach would result in an absurd height plane which would relate only to an existing building and have no relationship to the context of the site and its surrounds. 


Adopting the Applicant’s suggested approach of extrapolating from the footpath and surrounding sites, the Commissioner held (at [47]): 


“the level of the footpath at the boundary bears topography that includes the site, and remains relevant once the existing building is demolished.”


Accordingly, the approach proposed by the Applicant was considered a pragmatic method to determine ground level (existing) and has since become informally known as the “extrapolation method”.


Key Takeaways


  • Where an existing building occupies the entire site, it may be acceptable to extrapolate ground level (existing) from the level of the footpath at the boundary of the site and from levels on surrounding sites.


  • This is particularly preferable where determination of ground level (existing) from existing buildings would result in an inconsistent and irregular height blanket across a neighbourhood under the same development standard.


Stamford Property Services Pty Ltd v City of Sydney [2015] NSWLEC 1189 (Stamford Property)


Facts


Consent was sought for the partial retention and adaptive reuse of an existing building and construction of a 19 storey building with basement parking. 


Similar issues regarding the determination of existing ground level arose as in Bettar, although on a much larger site with a steep gradient. Calculating ground level (existing) with regard to existing built form, particularly basement levels on the site would result in irregular and inconsistent height controls across the site. 


Decision


The Court accepted the Applicant’s use of the Bettar extrapolation method to arrive at ground level (existing). In the circumstances, limited survey information was available and highly developed surrounding sites in the Sydney CBD made extrapolation difficult. Nevertheless, the Court noted that the extrapolation method was still possible with limited information and that there was sufficient actual and surveyed levels from the public domain in this case to arrive at a ground level (existing) figure for the (excavated) centre of the site, being an average between two survey points, rather than a surveyed (excavated) ground level. 


The Commissioner(s) held at [285]:


“… In our view, [the extrapolation method] … provides a practical operation to the definition [of ground level (existing)], both for a greenfield site and, as here, modified site in a built environment. It places the proposed building in its context, rather than relying on the present built form of any existing development on a site”.


Further, at [286]:


“Reliance on the existing built form … means that circumstances such as the extent of excavation from site to site could lead to different height limits applying to adjoining buildings on redevelopment of any of those sites. On the information available for the site, application of Bettar results in a sloping plane across the site, and we agree … that that reflects the relationship of the proposed development to the overall topography that includes the site.”


Key Takeaways


  • The “extrapolation method” is to be preferred where it can better place the proposed building in its context, rather than relying on the present built form of any existing development on a site.


  • The availability of survey information needed to apply the “extrapolation method” may vary from site to site and may include surveyed levels in the public domain, with a figure in the centre of the site being an average between two surveyed points rather than a surveyed ground level.


Land that has not been completely built out or excavated


Strebora Pty Ltd v Randwick City Council (No. 2) [2017] NSWLEC 1575 (Strebora)


Facts


Consent was sought for a four storey residential flat building over basement carparking on a site on which a residential dwelling (well set back from all boundaries) had previously stood. The Applicant contended that ground level (existing) should be determined by reference to levels from the street frontage rather than existing areas over parts of the site. The Applicant proposed taking the ground level at the street frontage and projecting that as a height plane across the site in elevations and sections.


Council contended that this approach was not usual practice and was not consistent with what was required by the LEP definition, particularly where survey information providing limited spot levels on the site showed that the ground level (existing) was beneath the Applicant’s projected height plane.


Decision


The Court held that the “extrapolation method” (from Bettar) was not directly applicable and was not appropriate in the circumstances. 


Because the residential dwelling had not occupied the entire site, there were patches of ground within the site that could be used to reference ground level (existing) and these were at street level. Further, the fall in the site also meant that it was not appropriate to determine the maximum allowable height from ground levels at the street frontage. 


Central to the Court’s finding is the notion that the determination of ground level (existing), must bear some relationship to the overall topography and context of the site. The Commissioner held at [58]:


“In these proceedings there are no facts that would preclude the applicant determining the lowest level on an existing site directly beneath the highest part of the proposed development, to determine a maximum building height dimension. In Bettar v Council of the City of Sydney the levels at the street/footpath were taken due to the fact that a building occupied the full extent of the land. This is not the case in these proceedings. I note at paragraph [37] Commissioner O’Neil recognises “that the determination of the existing ground level should bear some relationship to the overall topography that includes the site.” Given the fall across the land it is not sufficient to only determine the maximum height of the building at the street.”


Key Takeaways


  • The “extrapolation method” used in Bettar and Stamford Property cannot be used to arrive at artificial height planes across a site where parts of the site may be surveyed to give the existing ground level.


  • The determination of ground level (existing), must bear some relationship to the overall topography and context of the site and the “extrapolation method” may not be used where it would result in an artificial height plane that does not bear a relationship to the overall topography and context of the site.


Gejo Pty Ltd v Canterbury-Bankstown Council [2017] NSWLEC 1712 (Gejo)


Facts 


Consent was sought for construction of a 6-storey mixed-use building over two levels of basement carparking. The subject sites contained two existing dwelling houses and had not been extensively excavated or built upon. The sites were irregular and contained an unusual low point which gave rise to an irregular height blanket when applying the height controls in the LEP.


The Applicant contended that the irregular characteristics of the site meant that the method of calculation used in Stamford Property and Bettar should be applied in preference to the usual method of taking the lowest level on an existing site, as shown on the site survey, directly beneath the highest part of the proposed development.


Decision


The Court did not accept the method proposed by the Applicant, instead finding that the height of the proposed buildings should first be determined by applying the LEP controls. In circumstances where the site had not been extensively excavated and the ground level was known and able to be surveyed, the Commissioner held that the height of the building should be determined by the usual method. 


With respect to unusual slopes or grades and abnormal depressions in the site giving rise to unusual height limits, the Commissioner held at [25]:


“I do not accept that the method used by the Commissioners to calculate the ground level (existing) in Stamford Property Services Pty Ltd v City of Sydney and Bettar v Council of the City of Sydney overrules, or intends to overrule, the definitions contained in the relevant LEPs. This is clear from the comments in the joint judgment of Commissioner Pearson and Acting Commissioner Smithson at [283] of Stamford Property Services Pty Ltd v City of Sydney, in which they stated “the actual height of the proposed building must first be determined, by application of the 2012 LEP definitions.” The task undertaken by the Commissioners in those decisions is one whereby they found a way to apply the definitions contained in the LEPs in circumstances where the existing ground level is not known due to extensive development on the site. Given that there has been no extensive excavation of the site the subject of the current proposal, and the ground level is known and can be surveyed, the method used in those cases for calculating the ground level (existing) is irrelevant. Instead, the usual method of taking the lowest level on an existing site, as shown on the site survey, directly beneath the highest part of the proposed development reflects the definitions in the CLEP 2012 and should be used to calculate the building height. The fact that there is an uncharacteristic depression on the site is not relevant to this calculation, but might be relevant to the request to vary the height control considered below.”


Key Takeaways


  • Where ground level (existing) can be determined because the site has not been excavated or built upon, the extrapolation method is not intended, and should not be used to overrule the definitions contained in the relevant LEP’s. 


  • The fact that there are uncharacteristic depressions or irregularities on a site are not relevant to the calculation of building heights but will be relevant to a clause 4.6 request to vary the height controls.


Nicola v Waverley Council [2020] NSWLEC 1599 (Nicola)


Facts


Consent was sought for internal alterations and additions to a residential dwelling which included the addition of a new stair access with glass enclosure to the roof level and a new 15m2 rooftop terrace. 


An existing slab on the site made the determination of the ground level (existing) difficult. 


The Applicant contended that levels should not be taken from the existing slab and the extrapolation method should be used to take levels from the closest immediate proximity on the site where existing ground levels could be accurately determined. 


Council disagreed and argued that the use of the extrapolation method was inappropriate as the site had not been completely built out (as in Bettar and Stamford Property). 


The difference in competing interpretations determined whether the new addition of the glass stair enclosure was compliant with the height control. 


Decision


The Commissioner preferred the Applicant’s interpretation and held at [37] that the extrapolation method could be applied, even in circumstances where the site had not been completely excavated or built out:


“I agree … that the “extrapolation method” should be applied, based on the approach of selecting the levels located closest to the proposed stair enclosure. This is not inconsistent with the principle applied in Bettar and Stamford Property, which by necessity had to rely on the footpath levels outside the property boundaries because the buildings, in those cases, occupied the whole of their respective sites. In the subject development proposal the known ground levels identified are also outside the building and also closest to its exterior walls. The fact they are located within the site’s property boundaries, as opposed to outside the boundaries and on the footpath, does not derogate from the key selection criteria of closest immediate proximity.”


Key Takeaways


  • Where determination of ground level (existing) is made difficult by existing foundations or footings, it may be appropriate to use the extrapolation method either by obtaining levels from adjacent sites or within the site itself.


  • Where the particular circumstances of the case warrant the use of the extrapolation method, the levels to be used should be taken from the closest immediate proximity where existing ground can be found, whether that be within the site’s boundaries or outside the boundaries.


Summary


  • Where an existing building occupies the entire site, it may be acceptable to extrapolate ground level (existing) from the level of the footpath at the boundary of the site and from levels on surrounding sites.


  • This is particularly preferable where determination of ground level (existing) from existing buildings would result in an inconsistent and irregular height blanket across a neighbourhood under the same development standard.


  • The extrapolation method is to be preferred where it can better place the proposed building in its context, rather than relying on the present built form of any existing development on a site.


  • The availability of survey information needed to apply the “extrapolation method” may vary from site to site and may include surveyed levels in the public domain, with a figure in the centre of the site being an average between two surveyed points rather than a surveyed ground level.


  • However, the determination of ground level (existing) must bear some relationship to the overall topography and context of the site and the extrapolation method may not be used where it would result in an artificial height plane that does not bear a relationship to the overall topography and context of the site.


  • Where ground level (existing) can be determined because the site has not been excavated or built upon, the extrapolation method is not intended, and should not be used to overrule the definition and controls contained in local environmental plans.


  • The fact that there are uncharacteristic depressions or irregularities on a site are not relevant to the calculation of building heights but will be relevant to a clause 4.6 request to vary the height controls.


  • Where determination of ground level (existing) is made difficult by existing foundations or footings, it may be appropriate to use the extrapolation method either by obtaining levels from adjacent sites or within the site itself.


  • Where the particular circumstances of the case warrant the use of the extrapolation method, the levels to be used should be taken from the closest immediate proximity where existing ground can be found, whether that be within the site’s boundaries or outside the boundaries.


Require further assistance?


We have assisted many clients with issues relating to the determination of ground level (existing) and thus the applicable maximum building height of their proposed development. Often this can be a simple matter of engaging in constructive consultation with the relevant local council, or alternatively, bringing the matter before the Court for determination.


If you require advice regarding the determination of ground level (existing) of your site, or you wish to appeal against a determination of the issue by your local council, we can assist you in this process.



Please do not hesitate to call us on (02) 9145 0900 or make an enquiry below.

A man in a suit is sitting on the steps of a building.

Servicing all of NSW, Whiteacre provides expert property law and planning and environment law advice and assistance.

Planning Law Advice

Land and Environment Court Appeals

Voluntary Planning Agreements and Contributions

Development Control Orders and Enforcement

Property Development Advice and Due Diligence

Title Structuring

Easements and Covenants

Strata and Community Title legislation

Book an initial consultation through our website with our planning law solicitor. Whether it's about planning and environment law or property law, you can approach us and discuss your matter to make sure we are a good fit for your requirements.

BOOK ONLINE
By Mark Evans May 4, 2025
This article provides a general overview of the NSW Biodiversity Offsets Scheme, followed by a discussion of the tax implications of establishing a biodiversity stewardship site for Councils. What is the NSW Biodiversity Offsets Scheme? The NSW Biodiversity Offsets Scheme (the Scheme ) is a market-based scheme that is administered by the NSW Department of Climate Change, Energy, the Environment and Water ( Department ) and aims to help address the loss of biodiversity and threatened species in NSW. It seeks to do so by creating incentives for landowners to improve or maintain biodiversity values as a means of offsetting impacts on other areas. The Scheme is established by the Biodiversity Conservation Act 2016 ( BC Act ) . How the Scheme works Councils can establish a ‘biodiversity stewardship site’ ( Stewardship Site ) on eligible land within NSW by means of entering into a Biodiversity Stewardship Agreement ( Stewardship Agreement ) with the Department: s 6.17 BC Act. In doing so, Councils commit themselves to enhancing and protecting biodiversity values on the Stewardship Site. On execution of a Stewardship Agreement, the Council is entitled to receive an amount of biodiversity credits which are created by the Department. The amount of biodiversity credits are calculated by the Council’s accredited ecologist (and verified by the Department) in accordance with the methodology prescribed in the Biodiversity Assessment Method ( BAM ): s 6.7 BC Act. Biodiversity credits are created in respect of existing biodiversity values on the land and management actions to be carried out in accordance with the Stewardship Agreement. A biodiversity credit remains in force unless it is cancelled or retired: s 6.18 BC Act. The market value of the biodiversity credits is calculated by the Department at the time of creation. Sale and transfer of biodiversity credits Biodiversity credits may be sold by the Council to a buyer (or in parcels to a number of buyers) seeking to offset the impact of actions detrimental to biodiversity or to permanently secure conservation outcomes. The sale price of the biodiversity credits is determined by agreement between the Council and the buyer. Alternatively, biodiversity credits may be used by Council to offset negative biodiversity impacts arising from an activity carried out under Part 5 of the Environmental Planning and Assessment Act 1979 : s 7.15 BC Act. The Council may transfer biodiversity credits to a buyer or third party: s 6.19 BC Act. The transfer is made through an application to the Department by the parties to the transfer. The transfer is not effective until the transfer is authorised by the Department and registered in the register of biodiversity credits: s 6.20 BC Act. On the registration of the first transfer of the biodiversity credits, the Total Fund Deposit ( TFD ) specified in the Stewardship Agreement (or a proportion, if not all the credits are transferred) is required to be paid by the buyer of the biodiversity credits into the Biodiversity Stewardship Payments Fund (the Fund ): s 6.21 BC Act. The TFD is a fixed amount of money used to cover the long-term management costs of a Stewardship Site. It is a calculated value representing the present value of future payments needed to fund the agreed management actions. Contracts for the sale of biodiversity credits between the Council and purchasers will state that the credit owner is entitled to the full amount of the agreed sale price of the biodiversity credits, including the TFD, and that the credit owner will have the obligation to pay the TFD. Once the credits have been ‘used’ to offset negative biodiversity impacts and to permanently secure the conservation of biodiversity, they are ‘retired’ such that they can no longer be used for any other purpose: s 6.27 BC Act. Annual payments are made out of the Fund to the Council in respect of management actions carried out in accordance with the Stewardship Agreement: s 6.34 BC Act. Management actions typically include obligations to fence areas of land, control exotic pest species, carry out bushfire management and weed management. In summary, annual payments made out of the Fund can help Councils meet the expenses they currently incur managing large tracts of land while achieving significant biodiversity conservation outcomes. Disclaimer This is a general overview of the Scheme and tax implications. The information in this article is general in nature and is intended as a guide only. It is not designed to be, nor should it be regarded, as legal or accounting advice. The business and financial structure for each landholder or entity managing a biodiversity stewardship site or conservation area is likely to be unique. Therefore, the way taxation law applies will depend on individual circumstances and you should consult a professional tax adviser before engaging with the Scheme or entering into a Stewardship Agreement. Capital Gains The ATO deems that a capital gains event (type D4) occurs on entry into a Stewardship Agreement: s 104-47(1) ITAA. The landowner makes a capital gain if the “capital proceeds” are more than that part of the “cost base” of the land that is apportioned to the covenant. Most state and federal government departments, including local councils are tax exempt: s 50.25 ITAA. GST on entry into Stewardship Agreement When the Department and the Council enter into a Stewardship Agreement, the Council makes a taxable supply by entering into the agreement in return for the biodiversity credits issued by the Department and the Department makes a taxable supply of biodiversity credits in return for the Council entering into the agreement. These are non-monetary transactions. The Department and the Council (if both are registered for GST): are required to pay GST in respect of their supply, calculated on the estimated value of the credits; and can claim an input tax credit (ITC) in respect of the tax invoice received from the other party. If a Council is registered for GST, the Department will issue a Department GST invoice and Recipient Created Tax Invoice (RCTI) on behalf of the Council when the Department sends the registered BSA to the Council. The Department will use the estimated market value of the biodiversity credits for the purposes of these invoices. As the GST payable and the input tax credit that can be claimed are the same amount, the net GST position for both the Council and Department is zero. This means that these invoices do not need to be paid. However, both the Department and the Council are required to account for the GST payment and the input tax credit in their business activity statements (BAS). Capital gains from sale or transfer of credits A CGT event (type A1) occurs upon the sale of biodiversity credits. The Council may make a capital gain or loss depending on the capital proceeds and cost base of the credits: s 104-10(4) of the ITAA. A biodiversity credit constitutes a CGT asset: s 108-5 of the ITAA. CGT event (type A1) happens when the Council disposes of biodiversity credits: s 104-10 of the ITAA. Most state and federal government departments, including local councils are tax exempt: s 50.25 ITAA. GST on sale of biodiversity credits For the purposes of GST, the sale of credits is a taxable supply of goods. This means that the biodiversity credit price should include GST that the Council then needs to pay to the ATO. Receipt of annual payments from the Biobanking Trust Fund Annual payments from the Fund made by the Department to the Council are a contractual payment for the performance of services and should be ordinary income and assessable for income tax purposes. Most state and federal government departments, including local councils are tax exempt: s 50.25 ITAA . GST on annual payments The supply of stewardship services by the Council to the Department in return for payment of the annual payment should be a taxable supply. The Department will issue a recipient created tax invoice (RCTI) and include an amount for GST when making the annual stewardship payments for management actions the Council delivers. Conclusion Councils can establish biodiversity stewardship sites on eligible land within NSW by means of entering into a Biodiversity Stewardship Agreements with the Secretary of the Department. On execution of a Stewardship Agreement, the Council is entitled to receive an amount of biodiversity credits. Biodiversity credits may be sold by the Council to a buyer seeking to offset the impact of actions detrimental to biodiversity or to permanently secure conservation outcomes. Biodiversity credits may be used by Council to offset negative biodiversity impacts arising from an activity carried out by Council. Some of the proceeds of the sale of biodiversity credits must be paid into the Fund to cover ongoing management actions and costs. Annual payments are made out of the Fund to the Council in respect of management actions carried out in accordance with the Stewardship Agreement. Management actions typically include obligations to fence areas of land, control exotic pest species, carry out bushfire management and weed management. In summary, annual payments made out of the Fund could help Councils meet the expenses they currently incur managing large tracts of land while achieving significant biodiversity preservation outcomes. Disclaimer This is a general overview of the Scheme and tax implications. The information in this article is general in nature and is intended as a guide only. It is not designed to be, nor should it be regarded, as legal or accounting advice. The business and financial structure for each landholder or entity managing a biodiversity stewardship site or conservation area is likely to be unique. Therefore, the way taxation law applies will depend on individual circumstances and you should consult a professional tax adviser before engaging with the Scheme or entering into a Stewardship Agreement.
Navigating Land and Environment Court
By Mark Evans March 20, 2025
Expert Legal Insights on Development Approvals and Appeals with Planning Lawyer Mark Evans
Physical Commencement of Development Consents
By Mark Evans February 27, 2025
Development consents granted after 15 May 2020 face stricter requirements to determine whether they are substantially commenced and thus remain valid. This article reviews recent case law in New South Wales (NSW) and outlines the types of work that can qualify as physical commencement.
shared driveways
By Mark Evans February 13, 2025
Shared driveways A common example of a shared driveway is where a right of carriageway passes through one neighbours’ (burdened) land into the other neighbour’s (benefited) land.
tiny homes
By Mark Evans November 27, 2024
In Part 1, we considered tiny homes and caravans on private land. That article can be accessed here Part 1 . In Part 2, we turn our attention to tiny homes and manufactured homes.
tiny homes
By Mark Evans November 22, 2024
In this article we explore tiny homes, caravans, and manufactured homes.
By Mark Evans and William Jamieson November 14, 2024
The general rule is that a development application ( DA ) is to be determined based on the law applicable at the time of determination of the DA, not at the time of lodgement: Sofi v Wollondilly Shire Council (1975) 31 LGERA 416.
When subdivision may not be considered development carried out on land
By Mark Evans and William Jamieson October 31, 2024
Subdivision, alone, may not constitute development “on land” and thus trigger development restrictions. 
Biodiversity Credits
By Mark Evans October 18, 2024
The Independent Pricing and Regulatory Tribunal (IPART) has released a summary of workshops and stakeholders’ submissions concerning the functioning of the NSW Biodiversity Credits Market.
Development
By Mark Evans and William Jamieson October 10, 2024
It is now well established that a development consent cannot be obtained to authorise works that have already been carried out. The classic example is a building that has been built without development consent.
More Posts